We're working on the foundation! Setting out and we can dig

23/07/2024

The construction process is in full swing and the outlines of the multifunctional house are slowly but surely taking shape. The team has started by laying out the foundations and is gradually working on the base structure.

The foundations are laid out according to the so-called bench marks, which precisely define the boundaries for the foundation strips. Everything went smoothly thanks to the leveling machine we purchased last year for the workshop construction.

Thanks to the successful delivery of the building materials, the concrete pouring of the foundations has already begun. We are concreting up to a height of 40 cm without formwork directly into the excavated trenches for the foundation strips.

In the next few days we plan to finish concreting the foundation strips and gradually prepare the structure for the following foundation slab formation, so keep your fingers crossed!

We use cookies to enable the proper functioning and security of our website, and to offer you the best possible user experience.

Advanced settings

Zde můžete upravit své preference ohledně cookies. Následující kategorie můžete povolit či zakázat a svůj výběr uložit.